Mardi Clinic Refurbishment

Anthony Moran · Eleanor Duncan Aboriginal Services, Wyong · 5 Oct 2026 – 11 Nov 2026

ActiveAt risk

Complete

0%

0h of 405h

Hours remaining

405h

10 tasks

People

8 / 7

assigned / required

Days to handover

41

11 Nov

Schedule

Drag bars to adjust · linked tasks follow

Team

28 Sep
5 Oct
12 Oct
19 Oct
26 Oct
2 Nov
9 Nov
16 Nov

Ben Kavo

Head of Minor Works

0%
Site mobilisation · 6h/day
Client handover · 4h/day

Luke Newson

Pre-Construction Manager

0%
Programme and procurement · 3h/day

Anthony Moran

Head of Projects / Construction Manager

0%
Project controls · 3h/day

Chris Brown

Site Supervisor

0%
Services isolation · 6h/day
Quality inspection · 4h/day

William Chen

Carpenter

0%
Demolition and strip-out · 8h/day

Sam Lee

Carpenter

0%
Joinery installation · 8h/day

Michael Jones

Foreman

0%
Steel framing · 7h/day

Olivia Brewer

Financial Manager

0%
Mardi Clinic Refurbishment · 2h/day

Tasks

Risks & next actions

7
  • Ben Kavo is overbooked during "Site mobilisation"

    Open task
  • Luke Newson is overbooked during "Programme and procurement"

    Open task
  • Anthony Moran is overbooked during "Project controls"

    Open task
  • Chris Brown is overbooked during "Services isolation"

    Open task
  • William Chen is overbooked during "Demolition and strip-out"

    Open task
  • Michael Jones is overbooked during "Steel framing"

  • Chris Brown is overbooked during "Quality inspection"

    Open task