Mardi Clinic Refurbishment
Anthony Moran · Eleanor Duncan Aboriginal Services, Wyong · 5 Oct 2026 – 11 Nov 2026
Complete
0%
0h of 405h
Hours remaining
405h
10 tasks
People
8 / 7
assigned / required
Days to handover
41
11 Nov
Schedule
Drag bars to adjust · linked tasks followTeam
Ben Kavo
Head of Minor Works
Luke Newson
Pre-Construction Manager
Anthony Moran
Head of Projects / Construction Manager
Chris Brown
Site Supervisor
William Chen
Carpenter
Sam Lee
Carpenter
Michael Jones
Foreman
Olivia Brewer
Financial Manager
Tasks
- Site mobilisation
Ben KavoOverbooked
–5dh/day - Programme and procurement
Luke NewsonOverbooked
–28dh/day - Mardi Clinic Refurbishment
Olivia Brewer
–28dh/day - Project controls
Anthony MoranOverbooked
–28dh/day - Services isolation
Chris BrownOverbookedafter Site mobilisation
–2dh/day - Demolition and strip-out
William ChenOverbookedafter Services isolation
–5dh/day - Steel framing
Michael JonesOverbookedafter Demolition and strip-out
–5dh/day - Joinery installation
Sam Leeafter Steel framing
–6dh/day - Quality inspection
Chris BrownTentativeOverbookedafter Joinery installation
–2dh/day - Client handover
Ben KavoTentativeafter Quality inspection
–3dh/day
Risks & next actions
7Ben Kavo is overbooked during "Site mobilisation"
Luke Newson is overbooked during "Programme and procurement"
Anthony Moran is overbooked during "Project controls"
Chris Brown is overbooked during "Services isolation"
William Chen is overbooked during "Demolition and strip-out"
Michael Jones is overbooked during "Steel framing"
Chris Brown is overbooked during "Quality inspection"